Sunday, July 25, 2010

A LITTLE BIT HIGHER NOW

Now we are really able to tell the finished size of this closet addition. I hope all my shoes will fit. The trusses have been ordered for both the closet and the front porch and have been put into production. We anticipate having them delivered in two to three weeks. Our next big hurdles will be the glass block window installation, cutting out the new entry door in the old existing exterior wall and passing the lintel inspection.
































































































Monday, July 19, 2010

FRONT WALL TOPPED OUT

Panorama View . . .
Don't worry the bay window
is fine. The pictures didn't
get stitched together
properly.





Tim working hard before nightfall.















Profile of closet.













Tuesday, July 13, 2010

MORE BLOCK IN PLACE



Front Porch Foundation . . . waiting for next step.














More block laid yesterday . . .











With lots of sweat equity!!!

Wednesday, July 7, 2010

BLOCK GOING DOWN

Yesterday Tim was able to start laying the first corner of the new 'shoe' closet . . .















Wednesday, June 30, 2010

DELIVERY DAY

Today we received our delivery of block, sand, steel & cement.
















Guess I have work to do now. Chop. Chop.

Friday, May 7, 2010

Houston we have . . .


CEMENT!!!

The big pour day arrived yesterday. All went well. We had a crew in at 7:10am and then the cement truck arrived by 7:20am. The foundations look great. What a long day.


















Wednesday, May 5, 2010

Woo-Hoo and a Yiiippee ki-yay!!!


We have passed all inspections and are waiting for some cement!!!